When you’re planning a kitchen remodel, one of the first things you’re likely to wonder is, “How long is this actually going to take?” Knowing what to expect in terms of time can make a big difference in your planning, especially if you’re preparing for weeks without full use of your kitchen. Let’s dive into what the timeline for a kitchen remodel typically looks like, step-by-step.
Pre-Planning and Design (1-4 Weeks)
Before any demo or construction begins, there’s a lot of prep work involved. This phase includes gathering ideas, choosing a style, and working with a designer to map out what your new kitchen will look like. This stage can vary in length, depending on how clear your vision is and how quickly decisions are made. If you’re collaborating with a remodeling team, like those at Best Home Renovations, you can often get valuable advice on design, budget, and timelines.
Ordering Materials (2-8 Weeks)
Once the design is finalized, it’s time to order all the materials. Cabinets, countertops, appliances, tiles, and fixtures—these all need to be selected and ordered before construction begins. Depending on your choices, some items can take longer to arrive. Custom cabinets or specialty countertops may take longer to be delivered, so this stage can take anywhere from two to eight weeks.
Demolition and Prep Work (1-2 Weeks)
After all materials are ordered and the kitchen design is finalized, it’s time to get rid of the old. During the demolition phase, everything that won’t be part of your new kitchen layout gets removed, which can include cabinets, countertops, flooring, or even walls. Then, your remodelers will handle any electrical or plumbing work that needs updating.
Rough-In Work (1-3 Weeks)
This is when your remodel starts coming together. “Rough-in” refers to the installation of essential systems like plumbing, electrical wiring, and sometimes HVAC (heating, ventilation, and air conditioning). The complexity of the rough-in work can add a week or two, especially if your kitchen needs structural updates.
Installation (4-8 Weeks)
The installation phase is when you’ll really see your new kitchen take shape. Cabinets go in first, followed by countertops, flooring, lighting, and appliances. Each element has to be installed carefully to make sure it’s safe and up to code. This part of the remodel can take a few weeks, especially if your kitchen includes custom pieces or detailed features.
Finishing Touches (1-2 Weeks)
Finally, once the major installations are complete, it’s time for the finishing touches. This includes painting, installing backsplashes, and any final adjustments to cabinets, lighting, or other details. These small details wrap up the remodel and turn your kitchen from a construction site into a polished, new space.
Clean-Up and Final Walkthrough (1 Week)
The final stage involves cleaning up the space and making sure everything is working perfectly. Your remodeler will do a final walkthrough with you to address any remaining issues or touch-ups. With teams like Best Home Renovations, you can expect a detailed review of everything, ensuring your kitchen is ready to enjoy.
How Long Does a Kitchen Remodel Take in Total?
In general, you can expect a full kitchen remodel to take anywhere from 6 to 12 weeks from start to finish, depending on the complexity of your design and how smoothly everything goes. Homeowners in Gilbert, AZ, or anywhere nearby can streamline this process by working with experienced remodelers like those at Best Home Renovations, who understand the specifics of Home Remodeling in Gilbert, AZ.
More Stories
How to Choose a Pet-Friendly Apartment
Your Dream Wedding, Simplified: Why Choose an All-Inclusive Hotel Package
How to Choose the Right ECU for Your Vehicle